| Stadium Timeline |
| June 18, 1999 |
Groundbreaking |
| July 1999 |
Foundation construction begins |
| January 2000 |
Steel construction begins |
| October 2000 |
Steel "topped out" |
| May 2001 |
Turf installed |
| June 2001 |
Heinz gets naming rights |
| August 25, 2001 |
Stadium opening |
| October 7, 2001 |
Steelers Home Opener vs. Cincinnati Bengals |
| General Information/Facts |
| Owner: |
Sports & Exhibition Authority of Pittsburgh and Allegheny County |
| Developer: |
Pittsburgh Steelers |
| Events: |
Pittsburgh Steelers Football University of Pittsburgh Football Concerts Public Assembly |
| Architect: |
HOK Sports |
| Construction Manager: |
Hunt Construction Group/Mascaro (A Joint Venture) |
| Seating Capacity: |
65,050 seats |
| Club Seating: |
7,300(approx.) |
| Luxury Suites: |
1,544 (129 suites) |
| Building Square Footage: |
1.49 million sq. ft. (approx.) |
| Design Features: |
South End Plaza Great Hall - retail/entertainment area Horseshoe shaped stadium with south end open and on axis with Point State Park |
| Number of Club Lounges: |
One on each end of the east and west sidelines, as well as North end zone. The sideline ones are each designed as a three story atrium space with a large bar, beverage kiosks, specialty food stands and a video wall. Opportunities exist to convert the lounge into banquet space for large or small gatherings. |
| Restroom Facilities |
| Restroom Facilities (Including Club): |
24 women's, 24 men's and 8 family. Fixtures include 487 lavatories, 835 water closets and 204 urinals. |
| Concessions |
| Concession Stands: |
47 concession locations |
| Retail Stores: |
7 team stores |
| Novelty Stands: |
15 novelty locations |
| Locker Rooms |
| Steelers: |
6,000 square feet (60 lockers) |
| Panthers: |
4,600 square feet (95 lockers) |
| Visiting NFL Lockers: |
2,600 square feet (60 lockers) |
| Visiting College Lockers: |
2,600 square feet (60 lockers) |
| Vertical Tranportation |
| Elevators: |
7 passenger elevators 2 freight elevators |
| Escalators: |
5 |
| Pedestrian Ramps: |
4 |
| First Aid |
Minimum 1 on each level |
| Audio/Video |
| Television Sets: |
400 televisions linked to main scoreboard to automatically display special notifications about the game in progress. |
| Video Walls: |
2 |
| Scoreboard Video |
48 feet x 27 feet minimum |
| Playing Field |
| Natural Grass Playing Surface: |
2.04 acres (excluding warning track) |
| Sideline to First Row Spectator: |
60 feet |
| End Zone to First Row Spectator: |
25 feet |
| Construction Details |
| Cast in Place Concrete: |
48,000 cubic yards |
| Amount of Structural Steel: |
12,000 tons |
| Augercast Piles: |
10,442 lineal feet |
| Paint: |
30,000 gallons (provided by PPG Industries ) |
| Glass: |
50,000 square feet (provided by PPG Industries ) |
| Number of Doors: |
1100 |
| Miles of Railings: |
7 miles |
| Drainage, Irrigation and Heating Pipes Under the Field: |
1.85 miles |